23.09.26 - 11:30
|
Nordic Mining ASA: Legal proceedings initiated by EPC contractor (Cision)
|
|
|
Oslo, Norway – 23 September 2026
Nordic Mining ASA ("Nordic Mining") has been notified that its EPC contractor, Nordic Bulk AS, has initiated legal proceedings against Nordic Mining's subsidiary Engebø Rutile and Garnet AS ("ERG"), claiming payment of approximately NOK 50 million under the EPC contract for the Engebø Rutile and Garnet project.
ERG rejects the claim. The claim is partially rejected as unsubstantiated, and ERG has also withheld payments under the EPC contract pending Nordic Bulks rectification of defects.
The case will not affect operations at Engebø.
As...
|
|
|
22.09.26 - 15:18
|
Nordic Mining ASA: Notice of Extraordinary General Meeting (Cision)
|
|
|
Oslo, 22 September 2026
Shareholders in Nordic Mining ASA (the “Company”) (OSE ticker: NOM) are invited to attend the Extraordinary General Meeting to be held on 13 October 2026 at 15:00 (Oslo time). The general meeting will be held as a virtual meeting, where shareholders will be able to participate electronically via PC, phone or tablet.
Reference is made to previous stock exchange announcements regarding the Company's production ramp-up, liquidity and regulatory status. A comprehensive financial restructuring of the Company and its subsidiaries is required (the “Restructuring”)....
|
|
|
|
|
04.09.26 - 19:12
|
Nordic Mining: Update on liquidity situation and bondholder dialogue (Cision)
|
|
|
Oslo, Norway - September 04, 2026. Reference is made to the stock exchange announcements published by Nordic Mining ASA (“Nordic Mining” or the “Company”) and its subsidiary Engebø Rutile and Garnet AS (“ERG”) on 7 August 2026 regarding the Company's production ramp-up, liquidity situation and regulatory status.
As of today, Nordic Mining continues constructive dialogues with bondholders regarding a near-term financing solution through a potential tap issue. The dialogue with the bondholders, and other stakeholders, remains focused on reaching a solution within the coming days.
The...
|
|
|
|
|
|
|
|
|
|
|
18.08.26 - 08:06
|
Nordic Mining Q2 2026: Engebø ramping up, but slower than planned – The Company addressing liquidity and long-term financing (Cision)
|
|
|
Oslo, Norway – August 18, 2026 – Nordic Mining ASA ("Nordic Mining" or the "Company"), a resource company with focus on critical minerals, today released its financial results and operational update for the second quarter and first half of 2026.
Nordic Mining increased both throughput and production volumes at Engebø Rutile and Garnet (ERG) in the quarter. Following years of planning, permitting and construction, and with more than NOK 3 billion invested, Nordic Mining is leaving its capital-intensive stage and is now in a ramp-up phase at Engebø. The ramp-up has, however, progressed...
|
|
|
14.08.26 - 14:12
|
Nordic Mining ASA: Invitation to the presentation of the Q2 2026 results on Tuesday 18 August 2026 at 10:00 (CET) (Cision)
|
|
|
Oslo, Norway – August 14, 2026 - Nordic Mining ASA hereby invites you to the presentation of the results for the second quarter of 2026 and company update on Tuesday, 18 August 2026 at 10:00 (CET). The format of the presentation will be a live audio webcast. The interim report and presentation will be published on the NewsWeb and on Nordic Mining's webpage (www.nordicmining.com) on the same date and prior to the start of the presentation.
The presentation and Q&A session will be held in English. You will have the opportunity to submit questions online through the audio webcast. The...
|
|
|
07.08.26 - 08:00
|
Nordic Mining ASA – Update on Production Ramp-Up, Liquidity and Regulatory Status (Cision)
|
|
|
Oslo, 7 August 2026
INSIDE INFORMATION pursuant to Article 17 of the Market Abuse Regulation (MAR)
Nordic Mining ASA ("Nordic Mining" or the "Company") today publishes the following update regarding the production ramp up, liquidity and regulatory status. The Company is simultaneously publishing a separate stock exchange announcement from Engebø Rutile and Garnet AS (Nordic Rutile, ISIN: NO0012734112) as issuer of the Senior Secured Bonds.
Production ramp-up: The ramp-up at Engebø Rutile and Garnet AS ("ERG") is behind the original schedule. Following a ramp-up reset under new...
|
|
|
06.07.26 - 08:06
|
Appointment of financial advisers to support long-term development of Engebø (Cision)
|
|
|
Reference is made to the stock exchange notice 30 June 2026 regarding the Ministry of Climate and Environment's decision to uphold the discharge permit for the Engebø operation.
With the support, and a more predictable operational framework confirmed by the authorities, Nordic Mining is directing its attention to the long-term development of Engebø and the Company's broader asset portfolio.
The Company is currently ramping up production of rutile and garnet at Engebø. Rutile is a natural titanium feedstock, used in specialised industrial applications ranging from aerospace to pigments....
|
|
|
30.06.26 - 08:06
|
Ministry of Climate and Environment upholds Nordic Mining′s discharge permit (Cision)
|
|
|
Reference is made to the stock exchange notice 17 June 2026 regarding the Supreme Court's ruling in the dispute between the NGOs Friends of the Earth Norway (Naturvernforbundet) / Nature and Youth (Natur og Ungdom) and the Norwegian state.
Nordic Mining ASA ("Nordic Mining" or “The Company”) notes that the Ministry of Climate and Environment is upholding The Company's discharge permit while it carries out a renewed assessment of the permit in both the short and long term.
The decision helps secure a predictable framework for the company's operations at Engebø while the authorities...
|
|
|
25.06.26 - 12:24
|
Nordic Mining ASA; Receipt of claim for injunction (Cision)
|
|
|
Reference is made to the stock exchange notice 17 June 2026 regarding the Surpreme Court's ruling in the dispute between the NGOs Naturvernforbundet and Natur og Ungdom and the Norwegian state.
Neptun Network STI have today filed for an injunction against Nordic Mining with the claim that deposit of tailings in the Førdefjord from mining operations shall be prohibited. Nordic Mining will vigorously defend itself against the claim....
|
|
|
20.06.26 - 18:42
|
Nordic Mining applies for temporary discharge permit (Cision)
|
|
|
Reference is made to the stock exchange notice 17 June 2026 regarding the Norwegian State's loss in the appeal case against the NGOs. Nordic Mining ASA (“Nordic Mining” or the “Company”), has through its subsidiary Engebø Rutile and Garnet AS (“ERG”) submitted an application to the Norwegian Ministry of Climate and Environment for a temporary discharge permit, pursuant to Section 11 of the Norwegian Pollution Control Act.
The application concerns a temporary discharge permit for tailings from Nordic Mining's operations at Engebø, where the company produces rutile and garnet, critical...
|
|
|
17.06.26 - 20:06
|
Nordic Mining ASA: The Norwegian state loses appeal case against NGOs (Cision)
|
|
|
Reference is made to earlier stock exchange notices from Nordic Mining ASA ("Nordic Mining") regarding the legal dispute between the NGOs Friends of the Earth Norway / Nature and Youth and the Norwegian state regarding the validity of the discharge permit held by Nordic Mining's subsidiary Engebø Rutile and Garnet AS ("ERG").
The Norwegian Supreme Court has today ruled in favor of the NGOs concluding that the discharge permit is invalid. ERG is not a party to the case and the ruling is only binding on the state.
The Supreme Court limits its assessment to the reasons provided in the...
|
|
|
28.05.26 - 10:54
|
Nordic Mining ASA: Cancellation of the Subsequent Offering (Cision)
|
|
|
Reference is made to the stock exchange announcement published by Nordic Mining ASA ("Nordic Mining" or the "Company") on 16 January 2026 regarding a successfully placed private placement of new shares in the Company raising approximately NOK 200 million in gross proceeds by issuing 16,666,666 new shares, each at a subscription price of NOK 12.00 per share (the "Subscription Price") (the "Private Placement") and a contemplated subsequent offering of up to 10,833,333 new shares in the Company at the Subscription Price in the Private Placement, raising gross proceeds of up to approximately...
|
|
|
27.05.26 - 15:54
|
Nordic Mining ASA: Minutes from Annual General Meeting 2026 (Cision)
|
|
|
The Annual General Meeting in Nordic Mining ASA was held Wednesday 27 May 2026. All agenda items were approved in line with the proposals in the Annual General Meeting notice. The minutes from the Annual General Meeting in Norwegian and English are attached.
For further information, please contact CFO Tord Meling, telephone +47 990 98 766.
Oslo, 27 May 2026
Nordic Mining ASA
For more information, please visit www.nordicmining.com...
|
|
|
12.05.26 - 13:01
|
Nordic Mining: Share Capital Reduction Effective (Cision)
|
|
|
Oslo, 12 May 2026: Reference is made to the resolution by the extraordinary general meeting of Nordic Mining ASA ("Nordic Mining" or the "Company"), org.nr. 989 796 739, on 9 February 2026, to reduce the share capital by reducing the nominal value of the Company's shares from NOK 12 to NOK 1.20, cf. section 12-1 of the Norwegian Public Limited Liability Companies Act.
The share capital reduction was registered as effective with the Norwegian Register of Business Enterprises today, 12 May 2026, following which the Company's share capital is NOK 150,093,838.80 consisting of 125,078,199...
|
|
|
12.05.26 - 08:06
|
Nordic Mining Q1 2026: Operational improvements as focus shifts to mineral recovery (Cision)
|
|
|
Oslo, Norway – May 12, 2026 – Nordic Mining ASA ("Nordic Mining" or the "Company"), a resource company with focus on critical minerals, today released its first-quarter financial results and operational update. The quarter was characterized by meaningful operational improvements at Engebø Rutile & Garnet (ERG), with significantly improved uptime and throughput stability across the plant. With key bottlenecks now addressed, the Company's focus is shifting to lifting mineral recovery, which will be central to driving production volumes through the remainder of the year.
“In January we...
|
|