03.11.25 - 08:06
|
YIT to begin excavation work on the world′s largest seasonal heat storage – valued at approximately EUR 100 million for YIT (Cision)
|
|
|
YIT Corporation Investor News November 3, 2025, at 9:00 a.m.
YIT has been selected to carry out the excavation contract for Vantaa Energy's heat storage facility, Varanto, in Vantaa. The project is valued at approximately EUR 100 million for YIT. The project will be recorded in YIT's order book for the fourth quarter of 2025. Excavation work will begin in December 2025, and the contract is expected to last around three years.
Once completed, Varanto will be the world's largest seasonal heat storage facility, located deep beneath Ring Road III in Kuusikonmäki, Vantaa. The storage...
|
|
|
|
|
30.10.25 - 10:00
|
New high-quality homes in Vaasa - YIT started construction of Asunto Oy Vaasa Sommelier apartment building (Cision)
|
|
|
YIT Corporation Press Release October 30, 2025, at 11:00 a.m.
YIT has started the construction of the self-developed Asunto Oy Vaasan Sommelier apartment building in Klemettila, Vaasa. A total of 36 homes will be built in the five-story residential building. The value of the project is approximately EUR 8 million. The homes are slated for completion in the autumn of 2026.
The apartment building, located near the city center, will have around 1,600 square meters of living space. Vaasa's Sommelier apartments will be 25.5-75.5 square meters in size, and residents can select their new home...
|
|
|
30.10.25 - 09:00
|
New stylish homes in Tampere - YIT started construction of the Asunto Oy Tampere Sointu apartment building (Cision)
|
|
|
YIT Corporation Press Release October 30, 2025, at 10:00 a.m.
YIT has started the construction of the self-developed Asunto Oy Tampereen Sointu apartment building in Rauhaniemi, Tampere. A total of 55 homes will be built in the eight-story residential building. The value of the project is approximately EUR 16 million. The homes are slated for completion by the end of 2026.
The apartment building, located near Lake Näsijärvi, will have around 2,900 square meters of living space. The Tampereen Sointu apartments will range from 22 to 86 square meters in size, and residents may choose their...
|
|
|
30.10.25 - 07:48
|
YIT Corporation′s financial reporting and Annual General Meeting in 2026 (Cision)
|
|
|
YIT Corporation Stock Exchange Release October 30, 2025, at 8:45 a.m.
YIT Corporation's financial reporting and Annual General Meeting in 2026
YIT will publish the Financial Statements Bulletin for 2025 on Friday, February 6, 2026. Financial Statements 2025 will be published during week 9/2026 at the latest.
In addition, YIT will publish two Interim Reports and a Half-Year Report in 2026 as follows:
· Interim Report for January-March on Tuesday, April 28, 2026
· Half-Year Report for January-June on Friday, July 24, 2026
· Interim Report for January-September on Friday,...
|
|
|
30.10.25 - 07:30
|
YIT′s Interim Report January-September 2025 (Cision)
|
|
|
YIT Corporation Interim Report October 30, 2025, at 8:30 a.m.
YIT's Interim Report January-September 2025
Q3 profit driven by the contracting segments, Residential CEE growth continues
Third quarter of 2025 in brief
· Order book amounted to EUR 2,929 million (30 Jun 2025: 2,961). At the end of the period, 75% of the order book was sold (30 Jun 2025: 77%).
· Revenue decreased to EUR 402 million (453).
· Adjusted operating profit decreased to EUR 12 million (26). Adjusted operating profit margin decreased to 2.9% (5.6).
· Both revenue and adjusted operating profit...
|
|
|
23.10.25 - 09:12
|
Change in the Kemira Oyj′s Group Leadership Team: Tuomas Mäkipeska appointed Chief Financial Officer (Cision)
|
|
|
Kemira Oyj, Stock Exchange Release, October 23, 2025, at 10:10 a.m. (EEST)
Change in the Kemira Oyj's Group Leadership Team: Tuomas Mäkipeska appointed Chief Financial Officer
Tuomas Mäkipeska has been appointed Chief Financial Officer and a member of Kemira's Group Leadership Team. He will start in his new role no later than in May 2026. He succeeds Kemira's current Chief Financial Officer Petri Castrén who will leave the company, as announced earlier.
He joins Kemira from YIT Oyj where he has served as Chief Financial Officer and Executive Vice President & Deputy to the CEO...
|
|
|
23.10.25 - 09:06
|
Changes in the YIT Leadership Team: YIT′s Chief Financial Officer to change (Cision)
|
|
|
YIT Corporation Stock Exchange Release October 23, 2025, at 10 a.m.
Markus Pietikäinen, SVP, Treasury and M&A, at YIT has been appointed interim Chief Financial Officer and a member of the Group Leadership Team as of November 1, 2025. Tuomas Mäkipeska, CFO and member of the Group Leadership Team, has resigned from YIT to pursue his career outside YIT. He will leave the company in April 2026 at the latest.
Markus Pietikäinen has served as SVP, Treasury and M&A at YIT since the beginning of 2024. He joined YIT from Finnfund, where he was the Chief Investment Officer. Prior to his position...
|
|
|
23.10.25 - 08:06
|
Publishing of YIT Corporation′s January-September 2025 Interim Report on October 30, 2025 (Cision)
|
|
|
YIT Corporation Investor News October 23, 2025, at 09:00 a.m.
Publishing of YIT Corporation's January-September 2025 Interim Report on October 30, 2025
YIT Corporation's Interim Report for January-September 2025 will be published on Thursday, October 30, 2025, at approximately 8:30 a.m. EET. The stock exchange release and the reporting materials in Finnish and in English will be available at that time on the company's website at www.yitgroup.com/investors.
A webcast in English and an international telephone conference will be arranged on October 30, 2025, at 10:00 a.m. EET.
The...
|
|
|
20.10.25 - 09:06
|
YIT selected as main contractor for Kouvola data centre project (Cision)
|
|
|
YIT Corporation Investor News October 20, 2025, at 10:00 a.m.
The project company behind the Kouvola data centre initiative, Hyperco Fin HoldCo 1 Oy, has selected YIT as the main contractor for the construction of the facility. The project encompasses approximately 28,000 square metres and includes a data centre building, office premises, and associated external technical areas and site works.
“We are very pleased to be able to draw on Finnish construction expertise for the Kouvola project. Our cooperation with YIT strengthens the project's domestic content and boosts its employment...
|
|
|
17.10.25 - 07:01
|
YIT agrees on sale and construction of three residential buildings in Prague, Czech Republic – project value for YIT EUR 25 million (Cision)
|
|
|
YIT Corporation Investor News October 17, 2025, at 08:00 a.m.
YIT has signed an agreement with the Czech housing cooperative Ranta Barrandov IV for the sale and construction of three residential buildings.
Under the agreement, YIT will build 69 cooperative housing units in Prague, which the housing cooperative will sell to its members. The apartments are part of the popular Ranta Barrandov development, where YIT has previously built homes sold on the open market. The value of the agreement is approximately EUR 25 million, and the project will be recorded in YIT's order book for the fourth...
|
|
|
14.10.25 - 07:00
|
New seaside homes in Kivenlahti, Espoo - YIT launched the construction of a residential apartment building called Asunto Oy Espoon Vesta (Cision)
|
|
|
YIT Corporation Press Release October 14, 2025, at 8:00 a.m.
YIT has started the construction of a self-developed apartment building called Asunto Oy Espoon Vesta in the Marinranta block, in Kivenlahti, Espoo. A total of 30 homes will be built in the eight-story residential building. The value of the project is approximately EUR 15 million. The homes are slated for completion by the end of 2026.
The apartment building, located near the sea and the metro station, will house a living area of approximately 2,500 square meters. Espoo's Vesta apartments will be 59-148.5 square meters in size,...
|
|
|
|
|
15.09.25 - 11:01
|
YIT recognized as the most ideal construction industry employer for professionals for the sixth consecutive year (Cision)
|
|
|
IT Corporation Press Release September 15, 2025 at 12:00
Professionals in the field of engineering have ranked YIT as the most ideal employer in the construction industry for the sixth consecutive year in the Universum Professionals Survey. Also among students, YIT has maintained its position as the most attractive employer in the industry for seven years already.
“It is great that both professionals and students find YIT an attractive employer. Our success is based on skilled people, for whom we want to provide continuous development opportunities in a humane work community, supported...
|
|
|
11.09.25 - 17:01
|
Composition of YIT Corporation′s Shareholders′ Nomination Board (Cision)
|
|
|
YIT Corporation Stock Exchange Release September 11, 2025 at 6:00 p.m.
Composition of YIT Corporation's Shareholders' Nomination Board
YIT Corporation's three largest shareholders according to Euroclear's shareholder register on 29 August 2025 and according to the principles of the standing order have had the right to nominate representatives to the Nomination Board. According to the mentioned standing order, a shareholder group can agree on appointing a joint representative to the Nomination Board. The following shareholders have agreed on appointing a joint representative: PNT Group Oy,...
|
|
|
08.09.25 - 14:06
|
YIT and VTK Kiinteistöt Oy signed an agreement for the development phase of Tikkurila′s Competence Campus (Cision)
|
|
|
YIT Corporation Investor News September 8, 2025, at 3.00 p.m.
YIT and VTK Kiinteistöt Oy signed an agreement for the development phase of Tikkurila's Competence Campus
YIT and VTK Kiinteistöt Oy have signed a collaboration agreement for the development phase of The educational block of the Tikkurila competence campus area in Vantaa. The project will be implemented as a collaborative project management contract, including the development phase. The estimated target budget for the project management contract, determined by the customer of the project aiming at the implementation phase after...
|
|
|
29.08.25 - 12:01
|
YIT to build an expansion to Helsinki Expo and Convention Centre with the alliance model - the value to YIT approximately EUR 15 million (Cision)
|
|
|
YIT Corporation Press Release August 29, 2025, at 1:00 p.m.
YIT and The Finnish Fair Corporation have signed an agreement on the construction of an expansion to Helsinki Expo and Convention Centre (Messukeskus) with an alliance model in Pasila, Helsinki. The total value of the contract for YIT is approximately EUR 15 million, and it will be recorded in the order book for the third quarter of the year.
During the implementation phase of the Solar project, which is starting now, a new event space will be built at the south entrance of Messukeskus. The facades, steel frame and building...
|
|
|
28.08.25 - 07:02
|
YIT has signed a contract with JSC Lemora for construction of a warehouse in Kaunas, Lithuania – value for YIT over EUR 13 million (Cision)
|
|
|
YIT Corporation Press Release August 28, 2025, at 8:00 a.m.
YIT and one of the largest building and finishing materials trading companies in Lithuania JSC Lemora have signed a contract for construction of a warehouse for construction material storage purposes in Kaunas, Lithuania. The value of the contract for YIT is over EUR 13 million.
The scope of the project is approximately 15 000 square meters. The building will meet energy class A++ requirements. The construction works were started in August 2025, and the work is scheduled to be completed in September 2026.
For more information:...
|
|
|
26.08.25 - 11:36
|
YIT to build two apartment buildings in Helsinki – value to YIT approximately EUR 8 million (Cision)
|
|
|
YIT Corporation Press Release August 26, 2025, at 12:30 p.m.
YIT and Asumisoikeus Oy Helsingin Hirsipadontie 10 have agreed on the construction of a right-of-occupancy housing project comprising two apartment buildings in Helsinki. The project will be implemented as a turnkey contract, in which the builder is also responsible for the design of the site. Construction work will begin in August 2025 and the project is expected to be completed in October 2026. The contract value for YIT is approximately 8 million.
Asumisoikeus Oy Helsingin Hirsipadontie 10 covers approximately 3,300 square...
|
|
|
25.08.25 - 08:06
|
YIT is developing a new circular economy pilot block in Vallila, Helsinki (Cision)
|
|
|
YIT Corporation Press Release August 25, 2025 at 9:00 a.m.
YIT is launching the development of block 697 of approximately 1.5 hectares in Vallila, Helsinki. The goal is to create a more versatile and significantly greener urban block that will serve as a pioneer in sustainable urban construction and circular economy in construction. The project will be carried out in close cooperation with the City of Helsinki and experts in various fields.
The block owned by YIT since 2020 is located in the area delimited by the Teollisuuskatu, Sturenkatu, Elimäenkatu, and Telekatu streets. A reference...
|
|