23.11.26 - 14:36
|
Energy Vault Closes Non-Recourse Project Financing for 150 MW / 300 MWh SOSA Energy Center in Texas (Business Wire)
|
|
|
$78 million in construction and bridge financing supports the project's buildout
Bridge financing will be repaid with the already committed $80 million preferred equity investment on project completion
Additional draw on the existing OIC preferred facility funds the incremental equity for the project
Project expected to reach commercial operations in 3Q27, providing power and ancillary services to Texas' ERCOT North region. Construction ongoing and substation installed
Project is expected to deliver $250-300M+ in long term revenues while generating ~65% to 75% recurring EBITDA margins in line with all Asset Vault portfolio projectsWESTLAKE VILLAGE, Calif.--(BUSINESS WIRE)--Energy Vault Holdings, Inc. (NYSE: NRGV) (“Energy Vault” or the “Company”), a global energy infrastructure company supporting grid reliability and next-generation AI and high-performance computing infrastructure, today announced the closing of $78 million in construction and bridge financing for the SOSA Energy Center (“SOSA...
|
|
|
20.11.26 - 22:06
|
Energy Vault Holdings, Inc. Announces New Hire Awards Under NYSE Listing Rule 303A.08 (Business Wire)
|
|
|
WESTLAKE VILLAGE, Calif.--(BUSINESS WIRE)--Energy Vault Holdings, Inc. (“Energy Vault”) (NYSE: NRGV), a global energy storage company today announced that, effective on November 4, 2026, the Compensation Committee of Energy Vault's Board of Directors granted to 22 new employees restricted stock unit awards covering an aggregate 1,230,250 shares of its common stock under the Energy Vault Holdings, Inc. 2022 Employment Inducement Award Plan (as amended and/or restated, the “Plan”). The awards were granted as awards material to new employees entering into employment with Energy Vault in accordance with New York Stock Exchange Listing Rule 303A.08.
The restricted stock units vest over four years and are subject to the employee's continued service. The awards are subject to the terms and conditions of the Plan and an award agreement thereunder.
About Energy Vault
Energy Vault® is an integrated power infrastructure platform that builds, owns and operates flexible, reliable energy systems to accelerat...
|
|
|
|
|
|
|
|
|
|
|
|
|
10.11.26 - 22:06
|
Energy Vault Reports Third Quarter 2026 Financial Results, Affirms Recently Raised Full-Year 2026 Revenue Guidance and Provides Preliminary 2027 Financial Guidance (Business Wire)
|
|
|
Contract backlog reached $2.3 billion, up 15% sequentially and 147% year-over-year
Q3 2026 revenue of $13.1 million in line with consensus estimates
GAAP gross margin of 71.0% and adjusted gross margin of 81.1%. Excluding the benefit of tariff refunds, gross margins were 37.9% and 48.0%, respectively
Total cash increased to $236 million, up 59% sequentially and 281% year-over-year
Completed second portfolio acquisition of 2026 from Goshe Energy Storage (2.3 GW, including 350 MW ready to build); 100% of cash purchase price paid in Q3 2026
Received formal grid interconnection approval for 125 MW/1 GWh Stoney Creek project in Australia
Multiple project financings in U.S. and Australia underway
Affirming full-year 2026 revenue of $290–$310 million, at the top half of the previous guidance range with expected Q4 project deliveries supporting guidance
Preliminary full-year 2027 revenue and adjusted EBITDA guidance range of $600-$700 million and $40-$50 million, respectivelyWESTLAKE VILLAGE, Calif.--(BUSINESS ...
|
|
|
29.10.26 - 15:33
|
Eagle Point Provides Strategic Equipment Financing to Energy Vault for Behind the Meter Power Infrastructure (Business Wire)
|
|
|
GREENWICH, Conn.--(BUSINESS WIRE)--Eagle Point Credit Management LLC (“Eagle Point”), an innovative private credit investment manager, today announced it has provided a $137.5 million senior secured credit facility to a subsidiary of Energy Vault Holdings, Inc. (NYSE: NRGV) (“Energy Vault”), a global energy infrastructure company supporting grid reliability and next-generation AI and high-performance computing infrastructure.
Eagle Point directly originated and structured this bespoke financing, which will support Energy Vault's procurement of 275 MW of reciprocating engine generation capacity utilizing Rolls-Royce MTU technology for deployment across its hyperscale AI and data center infrastructure projects. Equipment deliveries are expected to begin in the second half of 2027 and continue through the first half of 2028. The transaction builds on Eagle Point's relationship with Energy Vault and was executed through collaboration across Eagle Point's Infrastructure Credit and equipment finance ...
|
|
|
14.10.26 - 15:30
|
Energy Vault Schedules Conference Call to Discuss Third Quarter 2026 Financial Results, Raises FY 2026 Revenue Guidance to the Top Half of the Previous Range (Business Wire)
|
|
|
WESTLAKE VILLAGE, Calif.--(BUSINESS WIRE)--Energy Vault Holdings, Inc. (NYSE: NRGV) (“Energy Vault” or “the Company”), a global leader in sustainable grid-scale energy storage and AI compute infrastructure solutions, announced today that the Company will release its earnings results for the third quarter ended September 30, 2026, on Tuesday, November 10, 2026, followed by a conference call at 4:30 PM ET.
The Company also raised its revenue expectations for the full year 2026 to the top half of the previous revenue range. During its Q2 2026 earnings call In August, the Company had previously raised and narrowed its FY 2026 revenue outlook from the prior range of $225-$300 million to $270-$310 million. Based upon current operational execution and expected Q4 project deliveries, the Company now expects revenue to finish at the top half of the previous range. The Company will be discussing more details on FY 2026 expectations on the November 10th Earnings Call while sharing initial guidance for FY 202...
|
|
|
|
|
|
|
|
|
|
|
22.09.26 - 15:06
|
Energy Vault Expands Asset Vault Platform with Portfolio Acquisition of Goshe Energy Storage, Adding More Than 2.3 GW of U.S. BESS Projects, Including 350 MW Ready to Build (Business Wire)
|
|
|
Portfolio includes two ready-to-build projects totaling 350 MW, both of which are expected to reach commercial operations in Q1 2028 and generate approximately $30 million of annual run-rate EBITDA
Goshe's leadership team and experienced development professionals are joining the Energy Vault team, with more than 75 years of combined experience in project development, BESS project management and financial services
Energy Vault secures credit facility commitment of up to $40 million from S2G Investments to support the development, construction and operations of the acquired portfolio
Acquisition accelerates the Asset Vault-specific annual recurring EBITDA timelines, now expected to generate $200M+ in 2028 exit run-rate EBITDA as part of its long-term energy infrastructure ownership modelWESTLAKE VILLAGE, Calif.--(BUSINESS WIRE)--$NRGV--Energy Vault Holdings, Inc. (NYSE: NRGV) (“Energy Vault” or the “Company”), a global leader in sustainable grid-scale energy storage and AI compute infrastructure so...
|
|
|
10.09.26 - 14:36
|
Energy Vault Closes Financing on 275 MW of Rolls-Royce MTU Reciprocating Engine Generation Capacity for Hyperscale AI Infrastructure (Business Wire)
|
|
|
275 MW of long-lead reciprocating engine generation capacity utilizing proven Rolls-Royce MTU technology secured for delivery from H2 2027 through H1 2028
Dedicated equipment financing secured from Eagle Point Credit Management LLC to support capital-efficient procurement and deployment
Strengthens Energy Vault's Powered Land solutions to accelerate speed-to-power supporting multi-GW project discussions for hyperscale AI campuses under developmentWESTLAKE VILLAGE, Calif.--(BUSINESS WIRE)--$NRGV--Energy Vault Holdings, Inc. (NYSE: NRGV) (“Energy Vault” or the “Company”), a global energy infrastructure company supporting grid reliability and next-generation AI and high-performance computing infrastructure, today announced that it has secured and fully contracted 275 MW of reciprocating engine generation capacity utilizing Rolls-Royce MTU technology. This procurement was supported by dedicated equipment financing from Eagle Point Credit Management LLC (“Eagle Point”). Equipment deliveries are ex...
|
|
|
04.09.26 - 04:03
|
Energy Vault beschleunigt Weg zur Bauphase von 125 MW/1 GWh Stoney Creek BESS durch Meilenstein für den vollständigen Grundstückserwerb des Projekts in Australien (Business Wire)
|
|
|
Energy Vault schließt Erwerb des zugrunde liegenden Projektgrundstücks nach Genehmigung durch FIRB-Regierung ab, wandelt bestehenden Pachtvertrag in Volleigentum an einem Grundstück und steigert Baureife für das 125 MW / 1 GWh Stoney Creek BESS Projekt
Baubeginn wird nun für das erste Quartal 2027 mit einem angestrebten Beginn des kommerziellen Betriebs im 1. Halbjahr 2028 erwartet; das Projekt wird durch 14-jährigen langfristigen Energiedienstleistungsvertrag (LTESA) unterstützt, was zu einem erwarteten jährlichen, langfristigen Umsatz von etwa 25 bis 30 Millionen US-Dollar pro Jahr führtWESTLAKE VILLAGE, Kalifornien--(BUSINESS WIRE)--Energy Vault Holdings, Inc. (NYSE: NRGV) („Energy Vault” oder das „Unternehmen”), ein globales Energieinfrastruktur-Unternehmen, das die Netzzuverlässigkeit und KI der nächsten Generation sowie die Hochleistungsrechner-Infrastruktur unterstützt, gab heute den Abschluss des Erwerbs des zugrunde liegenden Projektgrundstücks für das 125 MW/ 1 GWh Stoney C...
|
|
|
03.09.26 - 16:42
|
Energy Vault Accelerates 125 MW / 1 GWh Stoney Creek BESS Toward Construction with Full Project Land Acquisition Milestone in Australia (Business Wire)
|
|
|
Energy Vault completes acquisition of the underlying project land following FIRB government approval, converting from existing lease agreement to full land ownership, advancing construction readiness for the 125 MW / 1 GWh Stoney Creek BESS
Construction now expected to commence in Q1 2027, with commercial operations targeted for H1 2028; the project is supported by a 14-year Long-Term Energy Service Agreement (LTESA), providing expected annual, long-term revenue of approximately $25-$30 million per yearWESTLAKE VILLAGE, Calif.--(BUSINESS WIRE)--$NRGV--Energy Vault Holdings, Inc. (NYSE: NRGV) (“Energy Vault” or the “Company”), a global energy infrastructure company supporting grid reliability and next-generation AI and high-performance computing infrastructure, today announced the completion of the acquisition of the underlying project land for the 125 MW / 1 GWh Stoney Creek Battery Energy Storage System (“BESS”) in Northern New South Wales, Australia.
The land, which was previously secured un...
|
|
|
|