|
|
|
|
|
18.03.26 - 13:15
|
Blue Lagoon′s Milling Partner has Processed 3,000 Tonnes of Dome Mountain Material Producing Over 210 Tonnes of Gold & Silver Concentrate (The Newswire)
|
|
|
March 18, 2026 – TheNewswire - Vancouver, British Columbia – Blue Lagoon Resources Inc. (CSE: BLLG; OTCQB: BLAGF; FSE: 7BL) is pleased to provide an operational update from its milling partner, Nicola Mining Inc. (“Nicola”), regarding the ongoing processing of mineralized material from our Dome Mountain underground mine.
To date, Nicola has processed approximately 2,954 dry tonnes of Dome Mountain high-grade mineralized material at its milling facility in Merritt, B.C., at a weighted average feed grade of 9.7 g/t gold (Au) and approximately 35.6 g/t silver (Ag). This material has yielded over 210 dry tonnes of gold and silver flotation concentrate which is then bagged and readied for sale and shipment to Ocean Partners. Excellent gold recovery of 93.4% has been achieved in Nicola's flotation mill.
The 210 dry tonnes of concentrate produced to date is comprised of 188 physically bagged tonnes, with a further approximately 22 tonnes of concentrate currently held in the circuit stock tanks and repre...
|
|
|
|
|
|
|
|
|
20.02.26 - 14:00
|
Blue Lagoon Resources Completes Second Sale of $1.4 Million of Dome Mountain Mineralized Material - Milling Now Underway (The Newswire)
|
|
|
February 20, 2026 – Vancouver, British Columbia – Blue Lagoon Resources Inc. (CSE: BLLG; OTCQB: BLAGF; FSE: 7BL) is pleased to announce that it has received a second advance payment of ~ CAD $1.4 million from its milling partner, Nicola Mining, for 1000 tonnes of stockpiled mineralized material from the Company's 100%-owned Dome Mountain Gold and Silver Project.
To date, approximately 3,700 tonnes of Dome Mountain mineralized material have been delivered to the mill site and are currently stockpiled pending processing. Of this amount:
The Company previously received an advance payment for 1,000 tonnes.
It has now received a second advance payment for an additional 1,000 tonnes.
These advances are subject to final reconciliation following milling and settlement.
Processing of the Dome material was originally expected to occur earlier this month, however, to ensure the highest operational standards and recoveries, Nicola has conducted comprehensive plant cleanup and maintenance along with co...
|
|
|
|
|
|
|
|
|
29.01.26 - 14:00
|
Blue Lagoon Milling Partner Nicola Mining Shifts Focus Exclusively to Blue Lagoon′s Gold & Silver Mineralized Material (The Newswire)
|
|
|
January 29, 2026 – TheNewswire - Vancouver, British Columbia – Blue Lagoon Resources Inc. (CSE: BLLG; OTCQB: BLAGF; FSE: 7BL) continues to advance underground production at its 100%-owned Dome Mountain Gold & Silver Project as its milling partner, Nicola Mining Inc. (“Nicola”), begins to shift its milling focus exclusively to the Company's high-grade gold & silver mineralized material.
With no further third-party processing obligations, Nicola will now be dedicating its milling capacity to material delivered from Dome Mountain. This transition provides a more streamlined processing path as Blue Lagoon continues to advance underground operations and delivers mineralized material under its existing long-term milling agreement.
As previously reported, Blue Lagoon has already received a payment of nearly $1 million for its initial 1,000 tonnes delivered to Nicola in December and is continuing to build its stockpile, reflecting increasing underground output following the recent opening of m...
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
05.01.26 - 14:01
|
Blue Lagoon′s Underground Production Ramps Up (The Newswire)
|
|
|
January 5, 2026 – TheNewswire - Vancouver, British Columbia – Blue Lagoon Resources Inc. (CSE: BLLG; OTCQB: BLAGF; FSE: 7BL) continues to progress toward consistent mine production and regular deliveries of mineralized material to its milling partner, Nicola Mining Inc.
Following the holiday break, Dome Mountain has resumed production activity, which is set to increase as a result of several new operational measures detailed below. The mine is expecting to achieve consistent production of approximately 100 tonnes per day by month-end, positioning the Company to progress toward its fully permitted production level of 150 tonnes per day.
As outlined in the Company's President's Update of November 10, 2025, the early stages of ramping up underground mining at Dome Mountain experienced some timing delays. During this phase, a number of operational constraints typical of starting and commissioning an underground mine were encountered and our team identified and addressed these constraints. These cons...
|
|
|
30.12.25 - 14:01
|
Blue Lagoon Sells ~C$1 Million of Gold and Silver from Dome Mountain′s Initial Production to Ocean Partners (The Newswire)
|
|
|
December 30, 2025 – TheNewswire - Vancouver, British Columbia – Blue Lagoon Resources Inc. (“Blue Lagoon” or the “Company”) (CSE: BLLG; OTCQB: BLAGF; FSE: 7BL) is pleased to announce that it has made its first sale of gold and silver to Ocean Partners UK Limited (“Ocean Partners”) from the Dome Mountain mineralized material that was delivered earlier this month to the Company's milling partner, Nicola Mining Inc. (“Nicola”), for processing.
The Company expects to receive C$970,000 in connection with this initial delivery, representing its first sale related to production from Dome Mountain.
This payment represents an advance on the first shipment of approximately 1,000 tonnes of mineralized material delivered to Nicola, as processing has not yet occurred due to scheduled mill maintenance. Final settlement is expected following processing and is subject to customary adjustments, including final assays and prevailing metal prices at the time of settlement.
Following a brief Christmas...
|
|
|
|
|
15.12.25 - 14:15
|
Blue Lagoon Delivers 1,000 Tonnes to Milling Partner - Processing Expected to Begin by Week′s End (The Newswire)
|
|
|
December 15, 2025 – TheNewswire - Vancouver, British Columbia – Blue Lagoon Resources Inc. (“Blue Lagoon” or the “Company”) (CSE: BLLG; OTCQB: BLAGF; FSE: 7BL) is pleased to announce that it has now delivered its initial 1,000 tonnes of mineralized material from its Dome Mountain gold mine to its milling partner, Nicola Mining.
This delivery marks an important operational milestone in the Company's transition to production. With the initial tonnage now delivered, Blue Lagoon expects processing of Dome Mountain mineralized material to begin by the end of this week, subject to normal mill scheduling and planned maintenance activities.
“This is a significant milestone for Blue Lagoon,” said Rana Vig, President & CEO. “Delivering our initial 1,000 tonnes marks a key de-risking milestone and sets the stage for processing to begin by the end of this week. We are now on the doorsteps of a major transition - from a pre-revenue company to a revenue-generating gold producer, all against ...
|
|